Spine Line

The Spine Line is a new subway of about 25 miles under Western Avenue and 95th Street. It connects to every L line and forms a ring with the Red Line. Chicago voters vote on it first. The city pays for it with one citywide charge of about $1.49 a day, or $45 a month, for the median homeowner. The charge is the same for everyone and starts in the first year, so the city has to borrow less. It ends when the construction bonds are paid off, in about 33 years.

← ALL POLICIES

PART OF THE NEW BURNHAM PLAN

CONSTRUCT · ROOMS

Spine Line

A new subway lets you get across town without riding downtown first.

The Spine Line is a new subway, about 25 miles long, under Western Avenue and 95th Street. It has a transfer to every L line and opens in Year 5. It costs the median homeowner about $1.49 a day, or $45 a month, and you vote on it first.

Every L line is built to get you downtown, so crossing town means riding into the Loop and back out. That made sense when most people worked there. Now we're headed to childcare, a shift at a warehouse, our mom's place two neighborhoods over. More and more trips cross the city, and the train can't take you there.

The Spine Line runs under Western Avenue from Howard to 95th Street, then east under 95th to the Red Line at 95th/Dan Ryan. It has 24 stations and a transfer to every L line, and together with the Red Line it makes a ring around the middle of the city. You could ride from Rogers Park to Beverly without going downtown. Up top, Western gets rebuilt from end to end as a boulevard with trees, bike lanes and sidewalk cafes.

We build it the way Madrid did: our own engineers on the job from start to finish, one standard station design repeated down the line, and tunnel machines running around the clock. A contractor who finishes under the target cost keeps half the savings, so everyone has a reason to bring the price down. It's built with union labor at prevailing wage. The savings come from speed and good management, not from anyone's paycheck.

Everyone pays the same citywide charge: about $1.49 a day, or $45 a month, for the median homeowner, starting in the first year.

WHAT IT WON'T DO

It doesn't wait until the line opens to start paying. The city pays as it builds: the citywide charge starts in the first year, so the city borrows less and pays less interest: about $3 billion less in all than if the charge waited until the line opened. The bonds are paid off 30 years after the line opens, and then the charge ends (campaign estimate).

It doesn't happen without your say. The Spine Line goes on the ballot as its own question before anyone is charged anything.

It doesn't charge you more for living near a station. Everyone pays the same rate.

It doesn't wait on Washington. No federal grant is in the budget, so the project isn't stuck for a decade waiting on money that can be frozen after it's promised.

It doesn't shortchange your kids' schools. When property values rise along the line, Chicago Public Schools keeps its full share of the new tax money.

It doesn't push out the people already there. Before station locations are final, $100 million goes to community land trusts along the corridor, which buy and hold homes so they stay affordable. Residents and community groups get a first right to buy, and new buildings near stations include 30% affordable homes.

How it connects

Nothing in this plan works alone. These are the questions people ask next, and the policies that answer them.

What about the trains I ride now? Enjoy the Ride puts uniformed Transit Ambassadors and police officers on the trains, cleans every train at the end of the line and lights the 50 stations with the most crime, paid from money the CTA already has.

Enjoy the Ride →

What happens to Western Avenue up top? Paved Paradise rebuilds Western Avenue end to end, from the pipes up, while the subway is built beneath it. Yellow Brick Road corridors are streets where people walking and biking come first and cars can't cut through, and they connect neighborhoods to each other.

Paved Paradise →

Yellow Brick Road Corridors →

How are neighbors protected from being priced out where the city invests? Keep Chicago Chicago funds community land trusts, gives tenants the first chance to buy their building and protects longtime owners' property taxes, and if those aren't running, the project doesn't break ground.

Keep Chicago Chicago →

What else is on the same ballot, for rebuilding neighborhoods and paying off the pension debt? The Chicago Remodel Fund is a permanent property tax line that rebuilds neighborhoods from the pipes up and funds programs like mental health care, at about $1.75 a day, or $53 a month, for the median homeowner. Keeping Our Promises pays off the pension debt on a fixed 20-year schedule through its own line, the Pension Promise, at about $2.14 a day, or $65 a month, and the charge ends when the debt is paid.

Chicago Remodel Fund →

Keeping Our Promises: Paying Off the Pension Debt →

Who gets the jobs building it? The Chicago Trades Pipeline trains Chicagoans, with the unions, for careers rebuilding the city, including digging the subway, with no college debt.

Chicago Trades Pipeline →

FISCAL IMPACT

Revenue Generating

RENOVATION STEP

Construct · Rooms

SHOW THE FULL POLICY DETAILS

01

Where it ranks

OUR PRIORITIES

#5 of 33

TOP PRIORITY

73.8 / 100

Daily life

Long-term future

Reach

Unlocks

PROVEN The Spine Line is a new subway of about 25 miles under Western Avenue and 95th Street, with a transfer to every L line. It changes how the city moves for generations, because it connects neighborhoods to each other without going through downtown. The rest of the plan doesn't depend on it.

When you'd feel it: Year 5 or later.

See all the priorities

How I set them

02

How it works

The line

About 25 miles of subway (25.25 miles for costing): 21.4 miles under Western Avenue from Howard Street to 95th Street, 3 miles east under 95th Street to the Red Line's 95th/Dan Ryan station, and 0.9 mile along Howard Street to reach the Howard station. The line has 24 stations. Riders can transfer to the Red, Purple and Yellow lines at Howard; Brown at Western (Lincoln Square); Blue at Western on both the O'Hare branch and the Forest Park branch; Pink at Western (Pilsen); Orange at Western (49th Street); Green at a new transfer station at Lake Street; Red at 95th/Dan Ryan; and Metra's Rock Island Beverly Branch at 95th Street–Beverly Hills. With the Red Line at both ends, the two lines form a ring around the city's core. The whole line opens at once, not in phases.

South of 95th Street

The line ends at 95th/Dan Ryan; no extension to 119th Street or to the Red Line Extension is planned or budgeted (it would add about 3 to 3.5 miles). Morgan Park and the Beverly blocks south of 95th connect at a Beverly station at Western and 95th, by Pace #349 on Western, or by Metra's Rock Island Beverly Branch.

One team builds it

A Spine Line Delivery Authority, a public corporation owned jointly by the city and the Chicago Transit Authority (CTA), designs and builds the line and then hands it to the CTA to run. It keeps 100 to 150 permanent staff, including senior engineers paid competitive salaries so they stay for the whole job instead of rotating through consultants. Its board is appointed by the mayor and confirmed by the City Council, and it reports publicly every year on cost, timeline and performance.

Built the way Madrid built

The line uses one standard station design at all 24 stations. It uses design-build contracts, where one team both designs and builds. Eight tunnel-boring machines run around the clock with three rotating crews. Stations are dug open from the surface (cut-and-cover) where that is faster and cheaper. Bids are scored 50% on technical quality, 30% on price and 20% on schedule. A contractor who finishes under the $340 million-a-mile target keeps half of the savings. Illinois's prevailing wage law applies and the line is built with union labor; round-the-clock shifts are agreed with the building trades before the first contract.

The cost target

The target is $340 million a mile, about $8.6 billion in today's dollars. Per mile, that's roughly four times what Madrid paid in 1995-99 and a third of the Red Line Extension's cost. The public budget is $500 million a mile, about $12.6 billion today and $14.5 billion when built, assuming construction costs rise 4% a year.

Who pays

Chicago pays for the line with one citywide Spine Line charge, at the same rate for everyone. At the public budget, it raises about $896 million a year. For the median homeowner, that's about $1.49 a day, or $45 a month. There's no extra charge on homes or businesses near the stations. The value the line creates also helps run it. That value comes from 99-year leases on the air rights over stations (the city leases them instead of selling them), a share of development at stations, and part of the growth in property taxes along the line, with schools kept whole. That's about $1.9 billion over 25 years ($78 million a year, a campaign estimate).

When the charge starts and stops

The citywide charge starts in the first year and pays for construction as it goes, so less is borrowed: about $2.7 billion goes straight into building before the line opens. The bonds for the rest are paid off 30 years after the line opens, about 33 years after the first bill, and then the charge ends. Collecting from the first year costs about $3 billion less in all than waiting until the line opens (campaign estimate).

Schools are kept whole

When property values rise along the line, Chicago Public Schools keep their full share of the new tax money. Of what is left, 80% goes to the line, the same rule Chicago's two existing transit tax districts use.

Where the money goes

The money is spent in this order: first the bonds, then running the Spine Line, then improving the CTA and the Western corridor. The Spine Line sends no money to pensions. Pensions have their own voter-approved Pension Promise line, a separate property tax line under the Keeping Our Promises policy that pays the city's pension debt off on a fixed 20-year schedule and then ends.

No federal or state money budgeted

The plan budgets federal money at $0. State money is welcome but not counted. On the campaign's model, paying for the line ourselves costs the median homeowner about the same each day as waiting for a federal grant covering a third of the cost (a few cents less, because building later costs more), and the line opens five to eight years sooner. Our charge runs about three years longer, and over the life of the charge the median homeowner pays about $1,100 more in all. Once the city spends its own money on land or construction before a federal environmental review, federal money for the line is likely off the table; the plan accepts that trade.

Chicago votes first

The Spine Line is a citywide ballot question on the March 21, 2028 Illinois primary ballot, alongside the Chicago Remodel Fund (a permanent property tax line that pays for programs that keep families in their neighborhoods and rebuilds neighborhoods block by block) and the Pension Promise line, before anyone is charged. Each question stands on its own.

Western Avenue above the subway

Western Avenue is fully rebuilt from end to end while the subway is built, under Paved Paradise, the plan to rebuild each street once from the pipes under it to the sidewalk. The Spine Line's budget covers utility relocation and putting the street back at its station and shaft sites; Paved Paradise pays the difference to the full rebuild. The Spine Line runs its own business interruption fund for businesses near its station construction sites, modeled on Los Angeles Metro's.

Protections before the announcement

These protections are enacted before station locations are final: $100 million to community land trusts along the corridor, paid from the Spine Line's own budget the way its business interruption fund is (if the line comes in right at its public budget, that adds about a penny a day to the charge); a first right to buy for residents and community groups; deed restrictions that block resale for profit within 5 years on at-risk properties; 30% affordable units in new buildings within half a mile of a station; a 15-year freeze on property tax increases above inflation for homeowners of 10 years or more; rent stabilization for businesses that have been in the corridor 15 years or more; and 30% of construction jobs for corridor residents.

03

What it costs

Construction at the $340M-a-mile target (today's dollars)

About $8.6B

Construction at the $500M-a-mile public budget (today's dollars)

About $12.6B

Public budget when built (4% a year construction inflation)

About $14.5B

Paid in by the citywide charge before the line opens (first three years)

About $2.7B

Bonds issued for the rest, including interest during construction

About $12.8B

Bond payments at 5%, paid off 30 years after the line opens

About $835M a year

Running the line, after fares

About $139M a year

Value the line creates: air rights, station development, tax growth along the line (about $1.9B over 25 years)

About $78M a year

Federal and state money budgeted

$0

Community land trusts, funded before the announcement

$100M

Citywide Spine Line charge at the public budget

About $896M a year; about $1.49 a day ($45 a month) for the median homeowner

These are campaign estimates. The charge starts in the first year, pays for construction as it goes, and ends when the bonds are paid off, about 33 years after the first bill. Everyone pays the same rate. What the median homeowner pays depends on what construction costs per mile: about $1.04 a day at the $340 million target, $1.49 at the $500 million public budget, $2.05 at $700 million a mile and $2.89 at $1 billion a mile, which is typical for Chicago. If the state put in $1.5 billion, the public-budget figure would fall to about $1.34 a day. Together with the Chicago Remodel Fund ($1.75 a day) and the Pension Promise line ($2.14 a day), the median homeowner's three property tax lines come to about $5.38 a day.

How long we take to pay it off

Paying the bonds off faster costs more each month and less in all. Paying slower costs less each month and more in all, because the interest runs longer. We picked 30 years after the line opens: a subway serves a century of riders, and past 30 years, stretching it out barely lowers the monthly bill. For the median homeowner, at the public budget:

20 years after opening

Charge runs

23 years

A day

$1.74

A month

$53

In all

$14,600

25 years after opening

Charge runs

28 years

A day

$1.59

A month

$48

In all

$16,200

30 years after opening (our plan)

Charge runs

33 years

A day

$1.49

A month

$45

In all